Newly released emails show that government scientists working on the proposed nuclear waste dump site at Yucca Mountain in Nevada knowingly fabricated records in order to help the project move forward. In one email a scientist admitted “I’ve made up the dates and names… I will be happy to make up more stuff.” In another message the scientist wrote: “In the end I keep track of 2 sets of files, the ones that will keep QA happy and the ones that were actually used.” QA apparently refers to “quality assurance.” The emails were written in 1999 and 2000–during the Clinton administration. Yucca Mountain is the proposed site of an underground repository to hold some 77,000 tons of nuclear waste and used reactor fuel from commercial nuclear power plants. The project has been met by widespread fears that the plan to bury the nuclear waste is too risky.
Emails Showed Yucca Mountain Scientists Made Up Data
HeadlineApr 05, 2005